Future Pocket-Greenhaven LibraryPrint this article

Fact Sheet   Project Timeline   Architectural Drawings   Map

Building Progress
Date
 
Check back here often for updated images on your library’s progress!
  The groundbreaking celebration of the future Pocket-Greenhaven Library took place on Friday, May 30, at Sojourner Truth Park, in Sacramento. Over 200 excited community residents attended to watch the groundbreaking. Formal remarks were given by Library Director Anne Marie Gold, along with elected officials and Sacramento City Unified School District representatives.

  The groundbreaking marks the beginning construction phase for the following future projects: Sacramento City Unified School District’s School of Engineering and Sciences, Sacramento Public Library’s Pocket-Greenhaven Library, and City of Sacramento Department of Parks and Recreation’s Expanded Park and Play Fields at Sojourner Truth Park. The shared construction cost is $33.7 million.

Top






Pocket-Greenhaven Library Fact SheetPrint this article

Groundbreaking May 30, 2008
Square footage 15,000
Special features Leadership in Energy and Environment Design (LEED) certification, teen room, two group study rooms, a preschooler ready-to-read room, quiet reading room
Community meeting room 100-seating capacity
Public access computers 50
Collection(books, periodicals, DVDs, CDs, etc.) More than 50,000 items
Building architects WLC Architects, Inc.; Folsom
Electrical Engineer A & F Engineering, Inc.
Furniture design Flying Colors, Inc.; Berkeley
Interior signage Bess Design, Oakland
Total project cost $14,500,000
Funding City of Sacramento Community Reinvestment Capital Improvement Project Funds, Freeport Regional Water Authority Mitigation Funds, and City of Sacramento Council District 7 Discretionary Funds.
Top

Project TimelinePrint this article

Dates Description
February 2008 Programming & Schematic Design Work Completed
July 2008 50% Construction Drawings
October 2008 California Department of State Architects Plan Review
January 2009 – January 2010 Construction
Spring 2010 Library Grand Opening